400kV Transmission Line Fajr II, 27km Transmission line including
SSCO has been selected for the Construction of 400kV Transmission Line for Connection of Fajr petrochemical Power Plant to 400kV Mahshar Substation and Global Network
For the first time 400kV Telescopic Towers has been installed in this Project by SSCO And because of Swampy Ground 12km Piling and 22,000 m³ Concreting has been done.